BC NDP Leader David Eby announced a proposed “Built in B.C. and Canada” procurement policy on September 24, 2026, saying provincial ministries, Crown agencies and health authorities would be directed to prioritize B.C. and Canadian-made materials for public infrastructure projects where suppliers can meet competitive price and delivery requirements.
The party said the proposal was intended to direct more public spending to domestic businesses and support workers amid trade tensions with the United States.
The BC NDP said the approach would apply to ministries, Crown agencies and health authorities. The party also said it would immediately apply to the North Coast Transmission Line, with BC Hydro directed to build 70 per cent of Phase 1 towers and all Phase 2 towers using Canadian steel.
The announcement was a campaign commitment. It did not include draft procurement rules or establish that the proposed requirements had already taken effect.